top of page

BGS-GIMS campus

Project Brief

Construction of a medical university in the heart of the city is always a challenge owing to the space constraints. To add to this, a tight working schedule and strict deadlines makes the BGS-GIMS campus a very challenging and unique project. Protech has been instrumental in the overall planning and execution of this project to ensure all the statutory expectations were met by the client. 

Scope of works

  • Architectural service

  • Structural design

  • Civil works including finishes

  • Electrical - Internal and external

  • Plumbing - internal and external

  • HVAC

  • MEP

  • Interiors

Project details

Total Area - 7,00,000 sft

Duration - 36 Months

bottom of page